Question:
A project schedule has the following tasks:
– Task A takes 5 days and must be completed before Task B and Task C.
– Task B takes 3 days.
– Task C takes 4 days and must be completed before Task D.
– Task D takes 2 days.
What is the critical path?
Need a hint? Review the “must be completed before” tasks
– Task A takes 5 days and must be completed before Task B and Task C.
– Task B takes 3 days.
– Task C takes 4 days and must be completed before Task D.
– Task D takes 2 days.
Answer below…..
Answer: The critical path is A-C-D, which takes 11 days.